BUSKI East Wastewater Treatment Plant
240,000 m3 of wastewater is treated at the Bursa East Wastewater Treatment Plant on average.
Operation Start Date: May 2012
Operation Ending Date: December 2021
Population Equivalent: 1.550.000
Total Capacity: 240,000 m³/day
Project Description
Bursa East Wastewater Treatment Plant is built in accordance with the five-stage Bardenpho process (Phoredox) to serve a population equivalent of 1,550,000 residents. An average daily volume of 240,000 m3 of wastewater is treated at the plant.
The plant consists of the following units:
- Overflow Spillway,
- Coarse Grid,
- First-Stage Pumping Station, Fine Grids, Sand-Holding Tanks,
- Pretreatment Unit consisting of Second-Stage Pumping Station,
- Flow Measuring Channels,
- Selector and Anaerobic Tanks,
- Aerated Lagoons,
- Distribution and Collection Systems,
- Final Settling Tanks,
- Purified Water System,
- Service and Fire Hydrant Tank and Pumping Station,
- Return Activated Sludge Pumping Stations,
- High Return Activated Sludge Pumping Station,
- Sludge Grid System and Buffer Tanks,
- Sludge Dewatering and Lime Stabilization System,
- Ammonia Removal Unit,
- Overflow and Drainfield Pumps,
- Generator Buildings,
- Substation and Power Distribution Buildings,
- Operations Buildings and Ateliers,
- Auxiliary Buildings and Structures.